top of page
Writer's pictureFERA Ltd

JCA Phase VI: Schematic Design Stage




  • Develop Concept Design

  • 1:500 site plan

  • Develop 1:200 plans showing each room, all the lifts and stairs, doors, internal screens and windows with key furniture and fitting layouts

  • 1:200 drawings providing key travel distances for staff and patients and typical patient journeys

  • 1:50 key sections with detailed materials description

  • 1:100 elevations and sections

  • Door and window schedules

  • Key details: 20 number

  • Schematic landscape design proposals

  • Draft interior design strategy including wayfinding and finishes specification

  • 1:200 reflected ceiling plans

  • 6 CGI illustrations

  • Specification of Envelope, internal components



 


JCA Recommendation:


"We are fully aware that the key to your controlling your pre-construction costs is to transfer the production of information from the UK to Pakistan / Kashmir as early as possible whilst safeguarding quality. We suggest the following course of action and can talk around this next weekend.


As we outlined in our last email the next stage will be the Detailed Schematic Design Stage, the deliverables for which we have amended after thinking at what stage the scheme can be handed over to Kashmiri consultants .


We have based this phase of works on having the Concept design report formally approved, the appointment of all Kashmiri consultants, a revised Cost report confirming that there has not been project creep.


We propose that all the non-clinical parts of the building – see below - are developed by local architects to 1:50 room loading detail: Logistics / MEP plant / Offices / Education

We propose that these specialist parts of the building are developed as turnkey supplier and operator companies: Laboratories, CSSD


These proposals are put forward for comment and discussion. They are based on achieving a level of documentation that will allow the Smart Hospital project team to either commission a local consultant team to take the project to a traditional construction tender or go directly to a Design and Build Construction tender. It is assumed that in both cases JCA would be retained as expert advisors and quality control".



 